Energy Fuels Inc. Pinon Ridge Uranium Mill 2008 Pre-Application Documents

Licensing Process

Summary - Regulation of Uranium Recovery in Colorado

2008 Documents
December 18 Surface Water Sampling Work Plan - revision 3
November 14 Third Quarter 2008 Groundwater Monitoring Report

Appendix A - Daily Field Reports
Appendix B - Lithologic Log and Well Construction Details for MW-8B and MW-9
Appendix C - Monitoring and Production Well Construction Reports
Appendix D - Well Development and Sampling Field Sheets
Appendix E - Monitoring Well, Production Well, and Exploratory Boring Laboratory Analytical Results, QA/QC, and Chain-of-Custody

November 6 Second Quarter 2008 Groundwater Monitoring Report

Appendix A - Daily Field Reports
Appendix B - Lithologic Logs for MW-7 and MW-8A and Well Construction Details for MW-7
Appendix C - Well Development and Sampling Field Sheets
Appendix D - Lithologic Logs for the Exploratory Borings
Appendix E - Monitoring Well Laboratory Analytical Results, QA/QC, and Chain-of-custody

November 4 Ecological Screening of Raffinate Process Water
October 31 Geotechnical Design Recommendations

Appendix A - Vicinity Map, Boring Location Plan, Mill Pad Drainage and Grading Plan
Appendix B - Logs of Exploratory Borings    Available on CD - see instructions above
Appendix C - Laboratory Test Results   Available on CD
Appendix D - Augered Pressure Grouted Piles Allowable Capacity   Available on CD
Appendix E - Design Ground Motions   Available on CD

October 10 Roadway Pavement Design Recommendations

Appendix A - Vicinity Map, Locations of Borings and Test Pits, Pavement Design 
Appendix B - Logs of Pavement Borings and Pits      Available on CD - see instructions above
Appendix C - Laboratory Test Results    Available on CD
Appendix D - Roadway Thickness Calculations and Design Charts    Available on CD

October 9 Advance Copies of Design Reports
September

Phase 3 Long-term Pumping Test Data Report

Appendix A - Phase 1 Hydrogeological Testing Technical Memorandum
Appendix B - Phase 2 Hydrogeological Testing Technical Memorandum
Appendix C - Well Logs
Appendix D - AQTESOLV Analyses
Figures

 

September 24 Department Presentation at Uranium Recovery Workshop, Montrose, Colorado
September 8 License Application Schedule
August 27 Baseline Survey of Radionuclides in Animal Tissues at the Proposed Pinon Ridge Millsite
August 19 Department air permit requirements regarding Special Use Permit Application
August 14 Department Letter to Montrose County regarding Special Use Permit Application
July 22 Special Use Permit Application

Figures
Appendix A - Regulatory Requirements
Appendix B - Special Use Criteria
Appendix C - Legal Description and Property Ownership
Appendix D - Mill Components
Appendix E - Environmental Protection Measures
Appendix F - Closure and Reclamation Measures
Appendix G - Radiation and Worker/Public Safety
Appendix H - Full Size Drawings
 

July 18 Ambient Air Monitoring Plan

Figure 1 - included in Section 8.2
Figure 2 - Topographic Map
Figure 3 - Site Location
Appendix A - Site 1 Photographs
Appendix B - Site 2 Photographs
Appendix C - Site 3 Photographs
Appendix D - Site 4 Photographs
Appendix E - Site 5 Photographs
Appendix F - Laboratory Calibration QAPPs
Appendix G- Tisch Brushless VFC High Volume Air Sampler SOP
Appendix H - PM10 Federal Reference Method (FRM) Sampler SOP
Appendix I - Meteorological Station SOP
Appendix J - Rain / Snow Gauge SOP
Appendix K - Evaporation Gauge SOP
Appendix L - Auditor SOP

July 9 Additional actions to characterize groundwater at the Pinon Ridge Uranium Mill site
June 17 Adsorption Field Septic System Design

Post-Application Documents

2010 Documents
2009 Documents

Pre-Application Documents

2009 Documents

2007 Documents